Note: Dissemination levels follow the Horizon Europe definitions — Public (PU): fully open; Sensitive (SEN): available to consortium and granting authority only. This page is driven by a Markdown Content Collection and can be updated without rebuilding the site.
ID Deliverable WP Level Due Date Status Download
D1.1 Data Management Plan WP1 Public M06 (Aug 2025) Available PDF
D1.2 Project Management Handbook WP1 Sensitive M03 (May 2025) Available
D1.3 Quality Assurance Plan WP1 Public M06 (Aug 2025) Available PDF
D2.1 Substrate Characterisation Report WP2 Public M06 (Aug 2025) Available PDF
D2.2 Lab-Scale Process Protocols WP2 Public M18 (Aug 2026) Available PDF
D2.3 Pilot-Scale Validation Report WP2 Public M30 (Aug 2027) Pending
D2.4 Pre-Industrial Scale-Up Report WP2 Public M36 (Feb 2028) Pending
D3.1 Nutritional & Functional Profile Compendium WP3 Public M24 (Feb 2027) Pending
D3.2 Safety Assessment Dossier — Olive Pomace Protein WP3 Public M36 (Feb 2028) Pending
D3.3 Safety Assessment Dossier — Citrus Polyphenols WP3 Public M42 (Aug 2028) Pending
D4.1 LCA Methodology & System Boundary Report WP4 Public M12 (Feb 2026) Available PDF
D4.2 Comparative LCA — Pilot Scale WP4 Public M30 (Aug 2027) Pending
D4.3 Full Sustainability Assessment WP4 Public M45 (Nov 2028) Pending
D4.4 Techno-Economic Analysis Report WP4 Public M42 (Aug 2028) Pending
D5.1 Regulatory Landscape Analysis WP5 Public M12 (Feb 2026) Available PDF
D5.2 Novel Food Pre-Submission Consultation Report WP5 Sensitive M24 (Feb 2027) Pending
D5.3 Ingredient Dossier 1 WP5 Sensitive M42 (Aug 2028) Pending
D5.4 Ingredient Dossier 2 WP5 Sensitive M48 (Feb 2029) Pending
D5.5 Open Regulatory Decision-Tree Tool WP5 Public M48 (Feb 2029) Pending
D6.1 Communication & Dissemination Plan WP6 Public M03 (May 2025) Available PDF
D6.2 Project Website Launch WP6 Public M03 (May 2025) Available PDF
D6.6 Exploitation Plan WP6 Public M24 (Feb 2027) Pending
D6.7 Final Exploitation & Sustainability Report WP6 Public M48 (Feb 2029) Pending